Essential maintenance on the Incapsula data center in Dubai
Scheduled Maintenance Report for Imperva
Completed
Maintenance on the Dubai data center was completed. Network traffic has been restored.
Posted Feb 22, 2018 - 05:15 UTC
Update
Maintenance on the Dubai data center has been extended to 05:30 UTC.
Posted Feb 22, 2018 - 04:19 UTC
In progress
Maintenance on the Dubai data center has started. Network traffic has been diverted to an alternate regional data center. We expect the Dubai data center will be available by Wednesday, February 22nd, 2018 at 05:00 UTC.
Posted Feb 21, 2018 - 20:29 UTC
Scheduled
Maintenance on the Dubai data center will be performed on Wednesday, February 21st, 2018 at 21:00 UTC. We expect to complete the maintenance by Wednesday, February 22nd, 2018 at 05:00 UTC.
Posted Feb 21, 2018 - 06:52 UTC
This scheduled maintenance affected: EMEA PoPs (Dubai, UAE (DXB)).